Coke Oven Battery Thru Wall Rebuild - U.S. Steel, Clairton Coke Works - Pittsburgh, Pennsylvania

Project Description: 

Coke oven battery thru wall rebuild for U.S. Steel, Clairton Coke Works, in Pittsburgh, Pennsylvania: 2010-2013. Songer Services replaced 88 thru walls, while batteries were in operation. Project was 100% completed within the initial projected outage timeline of 70 turns per repair.  Songer Services completed each repair under the allotted 70 with a record of 56 turns.

Project Result: 

As noted in the project description, Songer Services beat the schedule a whopping 6 months early, saving U.S. Steel an estimated 30 million dollars.